| Programme duration | Ten days |
| Participants’ origin | Eighteen cities in Henan |
| Organisers | Henan Mine, the university and the special-equipment inspection institute |
Inspection practice connects with manufacturing
The programme brought together the manufacturer’s production environment, the university’s technical teaching and the institute’s inspection experience. Participants studied crane structures and inspection requirements within a working manufacturing setting.
Factory facilities and performance-testing equipment supported practical learning, connecting theoretical subjects with the components and machines inspectors encounter in their work.
Define what an inspection must establish
For a purchaser, inspection should be connected with the equipment specification and the stage of the project. Manufacturing review, factory operating tests and site commissioning answer different questions about the crane.
Agree which documents identify the materials, fabricated structure, mechanisms and electrical arrangement, together with the tests required before release. A purchaser-witnessed inspection should have a defined scope and acceptance criteria for the ordered equipment.
Coordinate factory and site checks
Include any destination-specific inspection requirements in the enquiry. Identify who will witness each stage and which checks remain after site erection, so the delivery and commissioning teams work from a common acceptance plan.