Two 40.5 t RMG Cranes for Taicang Port
Two rail-mounted container gantry cranes integrate variable-frequency motion, Siemens PLC, RCMS and truck-interface protection at Taicang Port.

The project and its handling task.
Henan Mine Crane supplied two rail-mounted container gantry cranes to Taicang Port, a logistics hub in the Yangtze River Delta. The project cranes are marked 40.5 t in their equipment photographs.
The systems combine variable-frequency drives, Siemens PLC and RCMS remote functions. Anti-sway, automatic container search, spreader zero-position monitoring, guidance and truck anti-lift protection address pickup, travel and placement. A ring-type trolley and interchangeable upper/lower-frame spreader arrangement accommodate different handling positions and cargo.
Keep container and mixed-cargo moves aligned with port traffic.
A busy port yard needs repeatable container stacking while leaving room for different cargo-handling attachments.
Set rail span, cantilever and truck clearances from the port layout.
Guide the container between the lane and assigned block with sway control.
Define a safe method for swapping lifting gear when non-container loads are scheduled.
Specify expected peak lifts per hour and available maintenance windows to plan crane duty and service access.

The equipment behind this project.
The systems combine variable-frequency drives, Siemens PLC and RCMS remote functions. Anti-sway, automatic container search, spreader zero-position monitoring, guidance and truck anti-lift protection address pickup, travel and placement. A ring-type trolley and interchangeable upper/lower-frame spreader arrangement accommodate different handling positions and cargo.
- Quantity2 rail-mounted container gantry cranes
- Equipment capacity marking40.5 t on each project crane
- Motion and controlVariable-frequency drives and Siemens PLC
- Remote functionsRCMS monitoring and operation
- Handling protectionAnti-sway, spreader guidance and truck anti-lift
- Attachment arrangementRing-type trolley and interchangeable upper/lower-frame spreader
What to compare with your own project.
Match the project configuration to your load, layout and operating sequence before selecting a crane package.
| Design area | This project configuration | Define for your site |
|---|---|---|
| Quantity | 2 rail-mounted container gantry cranes | Required crane quantity, yard coverage and simultaneous operating demand. |
| Equipment capacity marking | 40.5 t on each project crane | Required load rating and whether it is stated under the spreader or includes attachment mass. |
| Motion and control | Variable-frequency drives and Siemens PLC | Required motion speeds, drive-control functions, PLC interfaces and operating modes. |
| Remote functions | RCMS monitoring and operation | Operator location, permitted remote functions, monitoring data and communication interfaces. |
| Handling protection | Anti-sway, spreader guidance and truck anti-lift | Required anti-sway, spreader-guidance and truck anti-lift functions with agreed acceptance tests. |
| Attachment arrangement | Ring-type trolley and interchangeable upper/lower-frame spreader | Container and other cargo types, attachment interfaces, changeover procedure and tool mass. |
See the equipment and working environment.
Explore the equipment arrangement and handling environment.




Delivered and in use.
The two cranes were delivered on schedule and put into use at Taicang Port. They combine controlled movement, positioning and cargo-interface functions in one yard-handling package.
For a similar project, use rail-mounted gantries with controlled travel, anti-sway, truck protection and guided spreader positioning. Plan the trolley and exchangeable lifting gear for the actual cargo mix rather than assuming every move uses one spreader.
Prepare a comparable crane quotation.
Share the load schedule and site drawings. Use rail-mounted gantries with controlled travel, anti-sway, truck protection and guided spreader positioning. Plan the trolley and exchangeable lifting gear for the actual cargo mix rather than assuming every move uses one spreader.
We can quote a single crane or a coordinated fleet. The offer sets out the destination standards, required certificates and inspection records, manufacturing programme after drawing approval, shipment, installation support and agreed acceptance scope.
- Container and other cargo dimensions
- Rail and traffic layout
- Attachment changeover requirements
- Peak lifts and maintenance window
- Destination standards, quantity and inspection documentation
- Manufacturing programme, shipment, commissioning, training and spares
Questions before specifying a similar crane.
Can the same project crane be supplied for my site?
We customize the capacity, span, lifting height, attachment and controls to the load, building or yard layout and operating cycle. Container and other cargo dimensions are among the inputs to review before final equipment selection.
How are certification, quantity and lead time agreed?
Single-crane and fleet enquiries are welcome. Define the destination and required standards in the enquiry. The project offer confirms certification and inspection documents, the quantity, drawing approval and manufacturing schedule, with the shipping and site-service boundaries.
What should acceptance and after-sales support include?
Agree the inspection plan, representative load and functional tests, operator training, maintenance instructions, spare-parts scope and fault-recovery procedures. For this application, include peak lifts and maintenance window in the technical review.
Planning a similar lifting project?
Send your layout, load and operating requirements. We can develop a customized crane package and delivery scope for your site.