Specify the rail centre distance, the highest and lowest required hook elevations, and the load-and-rigging envelope against one agreed datum. Check roof clearance separately. Use the calculator below to compare a proposed vertical arrangement with your load path before choosing a crane configuration.
01What do crane span, lifting height and headroom mean?
Crane span is the centre-to-centre distance between the two runway rails. For an underhung arrangement, confirm the corresponding runway reference lines on its drawing. Building width, bridge length and usable hook coverage are different dimensions.
“Lifting height” needs a stated reference. Some catalogues use it for vertical hook travel; some layout discussions use it for the highest hook elevation above the floor. Record the two hook positions explicitly so the order cannot be interpreted either way.
| Dimension | Reference to put on the drawing | Decision it supports |
|---|---|---|
| Span, S | Runway rail centre to centre | Bridge/runway compatibility |
| Upper hook elevation | Hook saddle above the agreed floor datum at its upper working position | Clearing the load and rigging |
| Lower hook elevation | Hook saddle above or below that same datum | Reaching the lowest pickup |
| Hook travel | Upper minus lower hook elevation | Required vertical range |
| Building headroom above rail | Rail top to underside of the lowest overhead obstruction | Space for the crane above the runway |
A hoist’s C-dimension may be measured from its trolley-wheel running surface to the hook saddle. That running surface can be different from the crane runway rail. Use the dimension arrows on the offered drawing; do not subtract a hoist C-dimension from a runway elevation without accounting for the bridge geometry.
02How to check overhead crane span and usable hook coverage
For an existing runway, survey the rail centre positions and elevations along the bay. An old building drawing or a single width measurement cannot establish the complete installed alignment. Have the runway condition and supports checked against the proposed crane’s wheel loads.
For a new runway, calculate the proposed span from defined reference lines. If the column-centre distance is B, and the left and right rail centres sit inward by a and b, then S = B − a − b. The offsets come from the coordinated support and crane drawings. They need not be equal.
Illustrative plan: a 24.0 m column-centre spacing with 1.2 m and 1.4 m inward offsets gives a 21.4 m span. A blanket deduction from building width would miss that asymmetry. Once the rail centres are established, do not deduct end-carriage clearance again from the measured span.
Next, check the hook’s reach inside that span. Suppose the offered side approaches, measured from each rail centre, are 0.9 m and 1.1 m. The hook centre can cover 21.4 − 0.9 − 1.1 = 19.4 m across the bay. Using the left rail as x = 0, its interval is x = 0.9 to 20.3 m. A required pickup centre at x = 20.5 m lies 0.2 m beyond that interval even though the bridge fits.
Repeat this check along the runway using the bridge end approaches, stops and restricted zones. Plot pickup and set-down centres, then check the whole load envelope around them. Hook-centre reach alone does not establish clearance for a wide load, a turning load or its movement.
03Calculate hook height, travel and roof clearance
Use the actual proposed crane top elevation, including the effect of its installed runway height. A roof-based calculation alone gives a possible height ceiling; it does not prove that a crane on fixed rails can reach it.
The crane-top-to-hook dimension below combines the bridge, trolley and hook arrangement at the upper working position. Take it as one complete dimension from the proposed layout. Adding hoist-body height, C-dimension and hook-block height separately can count the same space twice.
PRELIMINARY LAYOUT CHECK
Overhead crane headroom calculator
Enter metres throughout, using the same finished-floor datum. These example values are illustrative. Replace them with your measured load path and the proposed crane drawing.
- Required upper hook elevation
- Proposed upper hook elevation
- Gap above crane / specified gap
- Minimum hook travel for these positions
View calculation and copyable summary
Calculate to compare the two hook elevations. Editing any input clears the previous result.
Formulas: required = Z + L + R + M; proposed upper hook = T − E; spare height = proposed − required; gap above crane = H − T (compare with C); required hook travel = required − Q. This is a vertical geometry estimate, not a crane or building design approval. It does not check span, wheel loads, deflection, sway, rigging capacity or operating limits. No values are sent.
JavaScript is needed for the calculator. The worked example below uses the same formulas.
Run the check for the most restrictive combination of load, lifting attachment and location. If different parts of the building have different floor levels, convert every elevation to the same datum first. All calculator entries use metres: 200 mm = 0.200 m.
04Worked example: enough hook travel can still leave a height conflict
Consider this illustrative arrangement. The dimensions explain the method; they are not a crane specification or prescribed clearance values.
| Input | Example |
|---|---|
| Lowest overhead obstruction above floor, H | 8.5 m |
| Specified gap above crane, C | 0.2 m |
| Proposed highest crane point above floor, T | 8.3 m |
| Crane top to upper hook saddle, E | 1.0 m |
| Surface to clear, Z / load height, L | 4.2 m / 1.8 m |
| Rigging height, R / transit allowance, M | 0.8 m / 0.3 m |
| Lowest required hook saddle, Q | 0.6 m above floor |
The load needs an upper hook elevation of 4.2 + 1.8 + 0.8 + 0.3 = 7.1 m. The proposed arrangement provides 8.3 − 1.0 = 7.3 m, leaving a 0.2 m preliminary height balance. Its top gap is 8.5 − 8.3 = 0.2 m, exactly the specified input. Required hook travel is 7.1 − 0.6 = 6.5 m.
Now increase the lifting attachment’s vertical space from 0.8 to 1.2 m. Required hook elevation becomes 7.5 m and travel becomes 6.9 m. A catalogue offer with 9 m hook travel can still fall 0.2 m short at the top. More rope travel does not move the bridge or hoist upward.
A pickup in a pit changes another part of the check. If the lowest hook position is −1.0 m instead of +0.6 m, the original 7.1 m upper requirement needs 8.1 m of travel. The roof and upper-hook requirements remain unchanged. This is why both endpoint elevations belong on the drawing.
05Which crane arrangement can recover useful height?
Compare drawings at the same capacity, duty and load path. A compact nameplate or a different girder count does not establish the final hook position.
| Option | Potential layout benefit | What to compare |
|---|---|---|
| Low-headroom single girder | A different hoist arrangement can reduce space above the hook | Complete top-to-hook dimension, side approach, reeving and service access |
| Double girder | The trolley/hook arrangement can use space between the girders | Hook elevation and crane top elevation together; the assembly may also extend higher above the runway |
| Underhung arrangement | A different support and travel arrangement may suit the building | Verified support capacity, total vertical envelope and required coverage; suspension alone does not prove a height gain |
| Different lifting attachment | A suitable arrangement may reduce hook-to-load distance | Approved rigging geometry, capacity and load control for the actual lift |
Review the low-headroom single-girder arrangement when the hoist envelope is the main constraint. Compare an electric-hoist double-girder arrangement when the trolley position or lifting task calls for another layout.
Lowering the runway can improve clearance above the crane while lowering the hook as well. Raising it can improve hook height while consuming roof clearance. Neither change is a general cure: coordinate the crane envelope, supports, services and required hook positions before changing the rail level.
06How do span and lifting height affect the price?
Longer spans change the bridge design, crane weight and wheel-load information that the runway designer needs. Greater hook travel can change rope storage, reeving and the hoist arrangement. A compact configuration can change the cost even when capacity and nominal lift remain the same.
For scale, an indicative new-equipment reference lists USD 3,130–8,680 for an LD-type 5 metric tonne single-girder crane family, across spans of 7.5–31.5 m and lifting heights of 6–30 m. This is a broad configuration range, not a paired comparison showing the cost of increasing span, and not a quote for the worked example.
The range does not establish freight, taxes, installation or runway-steel inclusions. Do not treat its lower end as an installed budget or infer a price per metre from its endpoints. A useful comparison fixes the capacity, duty, span, hook endpoints, power supply and control scope first, then separates the crane, rails/supports, transport and site work.
Use the overhead crane price guide to organise the budget scope. When height is tight, compare the cost of an engineered compact arrangement with the associated building or process changes, rather than choosing on the crane price alone.
07What should the layout drawing prove before you order?
A useful drawing links the plan and section views. The plan establishes where the hook can travel; the section establishes whether the complete load-and-rigging arrangement can pass through that area.
- Plan: runway reference lines, span, travel limits, side/end approaches and every required pickup or set-down centre.
- Section: agreed datum, rail elevation, lowest overhead obstruction, highest crane point, upper/lower hook saddles and the complete lifting attachment.
- Interfaces: wheel loads and their positions, runway/support details, power collection, services and access requirements.
Show the worst load orientation and any restricted areas. Account for the deflection, movement and installation tolerances required by the project’s design basis; the simple calculator does not supply those allowances. Use the same drawing references when comparing offers.
A phrase such as “21.4 m span, 9 m lift” still leaves the upper hook position unresolved. An illustrative clearer requirement is: “21.4 m rail-centre span; hook saddle must reach +7.1 m and +0.6 m relative to finished floor; verify the illustrated load path and roof envelope.” The supplier must then show the offered arrangement against those endpoints. Final acceptance also needs the structural and crane design checks applicable to that installation.
08Buyer questions
Is overhead crane span the same as the workshop width?
No. Crane span refers to the runway reference spacing, normally rail centre to centre for a top-running bridge. Workshop dimensions may be measured between walls, column faces or column centres. Use the actual rail positions or the coordinated support drawing rather than a universal deduction from building width.
Does a 9 m lifting height mean the hook reaches 9 m above the floor?
Only if the offer explicitly defines it that way. A 9 m hook-travel specification describes the range between two positions; it does not locate either position above the floor. Ask for upper and lower hook-saddle elevations relative to one datum.
Can a longer rope solve insufficient headroom?
More rope can extend downward travel if the hoist is designed for it. It does not raise the hook’s upper working position. An upper-height conflict needs a review of the crane arrangement, load path, lifting attachment or building geometry.
Is a double-girder crane always better in a low building?
No. Its trolley arrangement may improve hook height relative to the runway while its highest point also consumes more space above the rail. Compare the upper hook and crane-top elevations on drawings for the actual alternatives.
Can the headroom calculator confirm the crane is safe to install?
No. It compares a vertical load-path requirement with proposed crane dimensions and a specified top gap. It does not verify structural strength, runway alignment, wheel loads, rigging capacity, duty classification, deflection or operating limits. Those checks belong to the installation’s engineering and acceptance process.